FREW
Hong Kong Cut and Cover Tunnels – Frew Back Analyses
There have been numerous back analyses of Oasys Frew design outputs, including the Ashford Tunnel Box (Loveridge 2001). However, the more recent publication by Pan et al (2006) shows how Oasys Frew has been used and verified to analyse a challenging design problem and how its results are comparable with inclinometer readings.
Overview of the Project

The following case study summarises the paper linked below. The paper discusses a second rail border crossing between Hong Kong SAR and Mainland China that has been constructed.
The Kowloon Canton Railway Corporation (KCRC) constructed the Hong Kong section of the link, the 7.4km Lok Ma Chau Spurline. The design and build contract, ‘LBD201 - Sheung Shui to Chau Tau Tunnels’ forms part of the Spurline and comprises the design and construction of 3.6km of 8.75m excavated diameter twin bored tunnels and approximately 1.4km of cut-and-cover approach tunnels and associated structures.
This case study focuses on the back analysis of the particularly challenging East Approach cut-and-cover tunnels section of the project, which has recently been completed. The results of the back analysis showed the ground stiffness to be consistent with other published data.


Overview of the Geotechnical Solution
Ove Arup and Partners Hong Kong Ltd were commissioned by DJV to carry out the detailed design.
The method of construction and monitoring carried out to build the 700m long section of cut-and-cover tunnels to the north of Sheung Shui station has been described in detail by Storry et al (2005). Construction of the cut-and-cover tunnels involved excavations of upto 14m deep and 20m wide, within 1.5m of the live KCRC East Rail mainlines and within 1m of the Dongjiang Watermains, which supply Hong Kong’s potable water from China. Control of ground movements were therefore of prime concern to ensure that there would not be any disruptions to the daily.
Construction of the East Approach cut-and-cover tunnels was complicated by the need to construct within very restricted land boundaries and by the requirement that the construction of the new Spurline would not impact on the operation of the existing mainline. The final design required that two singlebox cut-and-cover tunnels be constructed side-by-side, both at different levels, ramping down into the main bored tunnels section

The full length of the East Approach cut-and-cover tunnels was split into several sections to facilitate construction. These were formed within temporary sheet-pile wall box excavations with the width varying from 8m to 20m. The figure below shows one of the strutted sheet-pile excavations under construction sandwiched between the live railway and the watermains.

Ground Monitoring
A highly developed system of monitoring instrumentation was a key component in satisfying the railway operator and Water Supplies Department (WSD) of the robustness of the design and the suitability of the construction methods to be adopted. The instrumentation included:
-
Ground deformation monitoring points on adjacent existing structures and utilities sensitive to movement;
-
Piezometers to monitor ground water levels around the excavations;
-
Inclinometers (installed within steel tubes that were welded and driven together with the sheet-piles) to monitor deflection of the temporary retaining walls; and
-
Real-time monitoring of the existing and diverted East Rail tracks.
-
Geotechnical Design
The design of the retaining walls and the strutting sequence was undertaken using the OASYS Frew software, which outputs the lateral displacement of the pile face. To convert this into vertical and lateral movements behind the wall, the recommendations of CIRIA Report C580 (2003), on the soil deformation analysis and radius of influence were adopted.
The effect on the groundwater was estimated using seepage analysis. Assumptions on the ground movement profile were verified using two-dimensional finite element computations undertaken in OASYS Safe.
Ground movement predictions were carried out based on free field predictions of movement. No account of structural stiffness was taken when assessing building, structure and utility movements, and therefore these predictions were considered conservative.

Back Analysis – Comparison to Ground Monitoring Data
Inclinometer monitoring of the sheet-pile wall confirmed that the displacements of the retaining walls were well within those predicted by the design.
Back analysis was carried out based on the observed wall deflections to determine the actual ground stiffness.
The construction sequence at these sections can be summarised as follows:
-
Install temporary sheet-pile walls and conduct pumping test to demonstrate water-tightness of the cofferdam;
-
Excavate and install temporary top strut, S1;
-
Excavate and install temporary lower strut, S2;
-
Excavate to the final excavation level and install base slab and lower wall;
-
Remove strut S2, and construct the remaining wall and roof slab of the permanent tunnel structure; and
-
Remove strut S1.

A comparison of the predicated and actual wall movements are shown.
It can be noted that the actual wall deflections were less than those predicted during design. This is considered to be due to the adoption of conservative soil parameters, actual ground water levels about 0.5m below the design water levels and live loads from the trains not being permanently applied.
Back analysis was carried out by enhancing the soil stiffnesses to obtain a best fit of the wall deflection profile. Corresponding wall deflections are shown below for steps taken to ‘match’ the measured wall deflections, which can be summarised as follows:
Step 0: Use actual ground water levels and ignoring live loads from trains.
Step 1: Increase stiffness of CDV to 4N.
Step 2: Increase stiffness of coarse alluvium to 4N.
Step 3: Increase stiffness of fill to 1.5N.

A detailed discussion of the back analyses is available in the Pan et al paper.
In general, the back-analysed stiffness values compare favourably with case histories of other excavation projects in Hong Kong and this approach was adopted for the design of the East Approach cut-and-cover tunnels.
As for the effects of wall friction, this is dependent on the condition of the sheet-pile and the method of installation. The back analysis demonstrates that the wall friction could lie between 0.5 and1.0 Æ’.
Construction
The LDB201 East Approach cut-and-cover tunnels have been successfully constructed within a narrow strip of land 1.5m from a live railway and 1m from one of Hong Kong’s primary water supplies.

References
Pan, J. K. L., Plumbridge1,G., Storry, R. B and Martin, O. (2006), Back Analysis of Cut and Cover Tunnels in Close Proximity to an Operating Railway in Hong Kong, Proceedings of the World Tunnel Congress and 32nd ITA Assembly, Seoul, Korea, 22–27 April 2006
Loveridge, F., (2001) Evaluation of Prop Loads at Channel Tunnel Rail Link Contract 430 – Ashford Tunnels,Ground Engineering, August 2001 Issue, pp38.
Storry, R.B., Scott, R., Martin, O., Wilmot, N. and Clayton, D. 2005. Challenges of Constructing a Cut-and-cover Tunnel Adjacent to a Live Railway in the Northern New Territories of Hong Kong SAR, Tunnelling for a Sustainable Europe (AFTES) Chambery, France.
CIRIA Report C580, 2003. Embedded retaining walls - guidance for economical design, CIRIA. United Kingdom
Credits
Geotechnical Engineers: Arup
Main Contractor: Drageges HK